Dholera International Airport Project

Dholera International Airport located at Navagam village near Ahmedabad, Gujarat is being developed by the Airports Authority of India (AAI) with a multi-phase master plan to ultimately handle 50 million passengers per annum in the future.

The greenfield international airport is being developed in Saurashtra within the Dholera Special Investment Region (DSIR) as part of the Delhi Mumbai Industrial Corridor (DMIC Corridor). The Dholera Airport will feature an aero city with 75 hectares for commercial developments, cargo facilities and ultimately two runways – 3200 m and 4000 m long.

Dholera Airport’s Phase 1 is expected to be completed and opened in March 2025 (current deadline).

  • Area: 1426 hectares
  • Estimated Cost: Rs. 1,378 crore (Phase 1)
  • Nodal Agency: Dholera International Airport Company Ltd. (DIACL)
  • Owner & Operator: Airports Authority of India (AAI)
  • Architect: Yet to be Appointed
  • Civil Construction Contractor: Yet to be Appointed


Current Status & Tenders

Dholera Airport

In January 2020, RITES emerged as the lowest bidder among 8 firms for its Engineering Consultancy contract.

In February 2021, AAI invited tenders for the construction of the airport’s infrastructure including runway, taxiways, aprons, perimeter road etc with an estimate of Rs 987 crore. Technical bids were opened in early June and saw 17 bidders participate. In June-end, Varaha Infra emerged as the lowest bidder for its construction work.

Scope: Development of New Greenfield Airport at Dholera, Ahmedabad (Gujarat). Phase-1. Detailed Designing, EPC of Airport infrastructure of operational area for 4E category operation of Airport i.e. Runway, Taxiway Apron, Perimeter Road etc., including associated Electrical works.

Dholera Airport Location & Access

The project’s site (view on Google Maps) is located north of Dholera Smart City & Bhavanagar, and south of Ahmedabad city. The site is accessible via NH-751 highway. In the future, Dholera Airport will be connected to Ahmedabad through the under construction 109 km Ahmedabad – Dholera Expressway and a semi high speed rail line. A monorail line has been planned, but will likely not be constructed.

Dholera International Airport Master Plan

Dholera Airport Plan

Dholera International Airport will be capable of handling 1.5 million passengers per year after the completion of its Phase 1 in 2025 and 50 million passengers per year after its final phase.

The final design of Phase 1’s terminal building has not been finalized. A tender notice for it is currently pending. Here’s the layout of the airport’s infrastructure and apron area:

Richers Realty Pvt.Ltd.